This Task Is Now Completed.
Work Order Owner :
Submitted by Admin
Submission Date :
December 17, 2024
Property :
6060 Schooner Dr Van Buren Twonship MI 48111 Belleville, Michigan 48111
Work Order Details :
Edit Info
Henry has details and blue prints please contact henry for this do not contact owner at this time.
Access & Contact Info :
Edit Info
call henry
Assigned Contractor :
Larry Shirley
Schedule :
Saturday, March 22, 2025 - 12PM - 3PM
Contractor's Quote:
25,000
Quote Details:
MATERIALS FOR WALLS:
pan head screws-4 boxes=$75
20-Gauge EQ Galvanized Steel Wall Framing Studs-(85)-$900
5/8 in. x 4 ft. x 12 ft. Firecode X Drywall-(60SHEETS)-$1400
4- five gallons of paint and primer-$600
mud, tape,sandpaper-$350
LABOR FOR WALLS: INSTALL APPROX 80 SHEETS FIRE RATED DRYWALL,METAL FRAMING STUDS, MUD TAPE AND SAN AND PRIME AND PAINT, INSTALL 6X6 BATHROOM WALLS, 8 DAYS LABOR, 5 GUYS-$14000
WALL HEATER MATERIALS: 100K BTU GARAGE WALL HEATER, GAS PIPE AND ELECTRICAL WHIP-$2700
WALL HEATER LABOR& PERMIT-$2100
PLUMBING MATERIALS: 3/4 PEX LINES, COPPER PIPE FROM MAIN, TOILET FLANGE, SINK TRAP-, sink, toilet-$1450
PLUMBING LABOR AND PERMIT-$3000
ELECTRICAL PERMIT AND MATERIALS- 6 LED CEILING LIGHTS, WIRE, JUNCTION BOXES, CONDUIT RUNS-$2500
Price is good for 20 days,
I5AA5
Canceled
Nothing to See Yet!
Contractors
_gif.gif)
I'm a paragraph.
This task already has a contractor. If you want to assign another contractor to this task, remove the current contractor
Assigned Contractor :
Larry Shirley
Contractor Removed!
Chat with the Investor
Message sent!
Chat with the Contractor
Larry Shirley : Please email details and drawings
🔴Larry Shirley : Called Sam no answer awaiting call back
🟢 Admin : Henry informed us that you and him will be walking this together
🟢 Admin : MATERIALS FOR WALLS:
pan head screws-4 boxes=$75
20-Gauge EQ Galvanized Steel Wall Framing Studs-(85)-$900
5/8 in. x 4 ft. x 12 ft. Firecode X Drywall-(60SHEETS)-$1400
4- five gallons of paint and primer-$600
mud, tape,sandpaper-$350
LABOR FOR WALLS: INSTALL APPROX 80 SHEETS FIRE RATED DRYWALL,METAL FRAMING STUDS, MUD TAPE AND SAN AND PRIME AND PAINT, INSTALL 6X6 BATHROOM WALLS, 8 DAYS LABOR, 5 GUYS-$14000
WALL HEATER MATERIALS: 100K BTU GARAGE WALL HEATER, GAS PIPE AND ELECTRICAL WHIP-$2700
WALL HEATER LABOR& PERMIT-$2100
PLUMBING MATERIALS: 3/4 PEX LINES, COPPER PIPE FROM MAIN, TOILET FLANGE, SINK TRAP-, sink, toilet-$1450
PLUMBING LABOR AND PERMIT-$3000
ELECTRICAL PERMIT AND MATERIALS- 6 LED CEILING LIGHTS, WIRE, JUNCTION BOXES, CONDUIT RUNS-$2500
🟢 Admin : Hello Larry the customer is asking for the bid can you send it please
Nothing to See Yet!
Message sent!