This Task Is Now Completed.
Work Order Owner :
Submitted by Admin
Submission Date :
January 27, 2025
Property :
8564 Windsor Court Ypsilanti MI 4819
Work Order Details :
Edit Info
Quote -drywall installation make sure to check roof for no leaks and confirm with owner that the roof is fixed
Access & Contact Info :
Edit Info
Leonard Casey- 734-612-7825
MUST BE THERE 3PM EXACTLY
Assigned Contractor :
Brian L Bond
Schedule :
Tuesday, January 28, 2025 - 3PM - 6PM
Contractor's Quote:
Ypsilanti
Quote Details:
Drywall, mud & sand walls 3000
Drywall, mud & sand ceilings 2000
Total labor 5000
Materials:
130 sheets drywall 1430
8 buckets joint compound 176
3 bags 45 min mix 36
2 rolls drywall tape 8
8 Sanding blocks 45
Total materials 1695
Grand Total 6695
______________________________________________
Additional quote:
Prime walls & ceilings 500
Paint walls & ceilings 1500
Total labor 2000
Materials:
7 gallons wall paint 230
5 gallons ceiling paint 120
5 gallons primer 105
Total materials 455
Grand Total 2455
J1UV1
In Progress
Nothing to See Yet!
Contractors
_gif.gif)
I'm a paragraph.
This task already has a contractor. If you want to assign another contractor to this task, remove the current contractor
Assigned Contractor :
Brian L Bond
Contractor Removed!
Chat with the Investor
Message sent!
Chat with the Contractor
Nothing to See Yet!
Message sent!