This Task Is Now Completed.
Work Order Owner :
Submitted by Admin
Submission Date :
December 22, 2024
Property :
17231 Wilson Ave, Eastpointe, MI 48021
Work Order Details :
Edit Info
Quote - Bathroom remodel will walk this with henry Appointment time 10:30am
Access & Contact Info :
Edit Info
Charles - 248-819-3022
Assigned Contractor :
Larry Shirley
Schedule :
Monday, December 23, 2024 - 9AM - 12PM
Contractor's Quote:
18500
Quote Details:
labor & materials-$
Move wall in master bedroom 41" inside 2nd bedroom, install barn door, closet off hall way door, remove closet in 2nd bedroom, install 48'' vanity, toilet, 5x3 walk in shower with niche, all plumbing, electrical and carpentry to turn master bedroom into a master suite, multiple areas in ceiling on first floor have to open to run drain lines, new attic access opening in master closet, ** owners will purchase and have delivered-ALL TILE,TOILET, VANITY, FAUCETS AND SHOWER DIVERTER WHICH WE WILL SEND SOME EXAPLES OF WHAT THEY SHOULD GET-
WE CITY STREETS CONTRACTING LLC WILL PURCHASE ALL OTHER MATERIALS FOR BUILD OUT
THIS IS A 2/3 WEEK JOB DEPENDING ON MATERIALS BEING DELIVERED BY OWNER
50% DEPOSIT BEFORE START AND AT 75% COMPLETION A 25% DRAW IS REQUIRED
P0XI0
In Progress
Nothing to See Yet!
Contractors
I'm a paragraph.
This task already has a contractor. If you want to assign another contractor to this task, remove the current contractor
Assigned Contractor :
Larry Shirley
Contractor Removed!
Chat with the Investor
Message sent!
Chat with the Contractor
Larry Shirley : Progress is in motion will upload when onsite each day
🔴Larry Shirley : Electrical is done starting to close walls tomorrow
Nothing to See Yet!
Message sent!